The second way is to go directly to the date column and select the employee for whom you want to modify the timesheet entry.
1. Click "Timesheets"
2. Click on the Date navigation
3. Select the date you want to create the timesheet entry
4. Click "Save" for the table to change
5. Click the "Search" field and find your employee by their name
6. Click the three-dot menu icon.
7. Click "Create"
8. Click "Add Project"
9. Select the project your employee worked on that date
10. Click "Next"
11. Click the "Select Time" field and add Start Time and End Time
12. Click "Add Break for project"
13. Select the time of the employee's break, you can add more than 1 if needed.
14. Click "Save"
15. You have successfully added a timesheet entry manually