How do I add budgeted quantities to an order on the dashboard?

A budgeted quantity is how much of an activity an order should deliver, for example 120 m³ of Excavation.

A budgeted quantity is how much of an activity an order should deliver, for example 120 m³ of Excavation. When you add budgeted quantities to an order on the Assignar dashboard, the Order Summary page shows how much has been done against each one as a percentage. You add them on the order's Activities tab in the Scheduler. Scheduler users who can edit orders can do this.

Your company can rename some words in Assignar, so you might see Job instead of Order. An activity (also called a cost code) is a type of work that workers and supervisors record time and quantities against.

Video (2:10): Setting budgeted activity quantities on an order.

Before you start

  • Each activity needs a unit. You can only budget an activity that has a Unit of Measure (for example m³, m or t). To check, go to Work Planning > Activities and look at the Unit column. To add one, open the activity and fill in Unit of Measure (20 characters or less). See How do I manage activities (cost codes) on the dashboard?.

  • Supervisors record progress in the Site Diary on the Assignar mobile app. Progress only counts against an activity that has a unit.

Add budgeted quantities to an order on the dashboard

To add budgeted quantities to an order on the Assignar dashboard:

  1. Go to Work Planning > Scheduler.

  2. Open the order's options menu and choose Edit order. To add quantities while creating an order, start a new order instead.

  3. Click the Activities tab ("Set your activities & estimated quantities.").

  4. Click the search box and type part of an activity's code or name. Pick the activity from the list (up to 25 matches are shown). It appears below with an Enter quantity box and its unit.

  5. Type the budgeted quantity as a whole number.

  6. Repeat for each activity on the order.

  7. Click Save Order.

The activities now appear on the order's Order Summary page with "[done] / [budget] [unit] ([percentage]%)" and a progress bar.

Activities tab of the order form in the Scheduler with Excavation and a budgeted quantity

Add an activity to an order without a budget on the dashboard

On the Assignar dashboard you can add an activity to an order's Activities tab without a quantity. Supervisors can still record progress against it in the Site Diary, and the Order Summary page shows the quantity done, but no percentage or progress bar. An activity with no unit shows No quantity and the box can't be filled in.

Change or remove a budgeted quantity on the dashboard

To change or remove a budgeted quantity on an order on the Assignar dashboard:

  1. Open the order with Edit order in the Scheduler and click the Activities tab.

  2. To change the budget, type the new number in the activity's box.

  3. To take the activity off the order, click its bin icon.

  4. Click Save Order.

Progress already recorded in Site Diaries is not deleted.

Import activities and quantities into an order on the dashboard

To add many activities and quantities to an order on the Assignar dashboard at once, click Import on the order's Activities tab, follow the import window, and click Submit Activities. The import window checks each row and shows:

  • "New activity will be created" or 'Linking to "[activity]"' for rows it can use.

  • "Need a code to add this activity", "Need a name to add this activity" or "Need units to add this activity" when a column is empty.

  • "Quantity must be a positive number".

  • "The code cannot be over 100 characters", "The name cannot be over 100 characters" or "The unit cannot be over 20 characters".

  • "This activity was found as inactive, please reactivate it to import".

  • "Activity already exists on the order".

If some rows fail, the dashboard shows Import Warning with "Some activities could not be imported: …". If none work, it shows "No activities could be imported, please try again."

Why can't I add a budgeted quantity on the dashboard?

These are the common reasons a budgeted quantity can't be added to an order on the Assignar dashboard:

  • The box says "No quantity" and is greyed out. The activity has no Unit of Measure. Add one in Work Planning > Activities, then open the order again.

  • "Activity already added": the activity is already on the order. Each activity can only be on an order once. Change the existing quantity instead.

  • "Only one of each Activity can be assigned to an Order.": the same activity was added twice. Remove one.

  • "Cannot set a quantity to Activities without UOM.": an activity with a quantity has no unit. Add a unit to it or clear the quantity.

  • The activity isn't in the list. It may be inactive, or already on the order. Inactive activities can't be added.

  • You can't edit the order. Users with the Read Only access module see the order as read only.