How do I track activity progress on an order on the dashboard?

The Activities tab on an order's Order Summary page on the Assignar dashboard shows, for each activity, how much has been done against its budgeted quantity and how many labour hours have gone into it.

The Activities tab on an order's Order Summary page on the Assignar dashboard shows, for each activity, how much has been done against its budgeted quantity and how many labour hours have gone into it. Anyone with access to Orders or the Scheduler can see it. The quantities done come from the progress supervisors record in the Site Diary on the Assignar mobile app.

Your company can rename some words in Assignar, so you might see Job instead of Order. An activity (also called a cost code) is a type of work, for example Excavation.

Video (3:06): Tracking activity progress on an order.

See activity progress on an order on the dashboard

To see the progress of each activity on an order on the Assignar dashboard:

  1. Open the order's Order Summary page. In the Scheduler, point at the order's row and click the chart icon (Open Order Summary).

  2. In the Progress section, click the Activities tab.

Each row shows the activity's code and name, and:

  • With a budgeted quantity: "[done] / [budget] [unit] ([percentage]%)" and a progress bar. The done figure turns red when it is more than the budget. The bar stops at 100%.

  • With progress but no budget: the quantity done and the unit, with no bar.

  • With neither:No Quantity.

  • Labor Hours: the hours from timesheets submitted against the order with that activity.

Percentages are rounded to two decimal places. A percentage between 0% and 0.5% shows as 1%, and one between 99.5% and 100% shows as 99%, so an activity only shows 100% when it is finished.

Activities tab on the Order Summary page with progress bars against budgeted quantities

Search and sort activities on an order on the dashboard

To find an activity on the Activities tab of the Order Summary page on the Assignar dashboard:

  • Search: click the search icon and type in Search for Activity Name.

  • Sort: open the sort menu and choose First Added, Code, Progress or Labor Hours.

See each progress entry for an activity on the dashboard

To see every progress entry recorded for one activity on the Assignar dashboard:

  1. On the order's Order Summary page, click the Activities tab.

  2. Click the activity's row. You can only click activities that have a budget or some progress.

  3. The progress log opens with the activity's total at the top. Each entry shows Date, Quantity, Created By, Comment and Photos.

  4. To see the photos for an entry, click "[number] Images".

  5. To open the Site Diary the entry came from, click the entry. It opens in a new tab. You need access to Site Diaries to do this.

  6. To go back to the list, click the back arrow.

Export progress transactions for an order on the dashboard

To download every progress entry on an order as a CSV file from the Assignar dashboard:

  1. On the order's Order Summary page, click the Activities tab.

  2. Click the options menu (three dots) at the top of the tab and choose Export Progress Transactions.

  3. The dashboard shows Export in progress... and "Exporting into your browser, just a moment!". The file downloads when it is ready, and the dashboard shows "Export has been completed!".

To stop the export, cancel the dialog. The dashboard shows "Export has been canceled.".

Why is activity progress missing or wrong on the dashboard?

These are the common reasons activity progress on an order's Order Summary page on the Assignar dashboard looks wrong:

  • An activity shows a quantity but no percentage or bar. It has no budgeted quantity on the order. Add one: see How do I add budgeted quantities to an order on the dashboard?.

  • An activity shows only Labor Hours. Nobody has recorded progress for it in a Site Diary, or the activity has no unit, so progress can't be recorded against it.

  • Progress is missing for a day. Progress only counts once it is recorded in a Site Diary for this order. A deleted Site Diary's progress is not counted.

  • Labor Hours look low. Only timesheets submitted against this order with this activity count.

  • "No Activities Found.": the search box doesn't match any activity, or the order has no activities, progress or timesheets yet.

  • "Failed to fetch order activities: …" or "Failed to export: …": the page couldn't load or export. Refresh the page and try again.