Open Task Management > Task Assignments. Four summary cards appear at the top.
Today's Tasks — number of tasks assigned and workers assigned
Assignment Coverage — how many workers received an assignment, out of all workers
Confirmations — how many assigned workers have confirmed. Click to see who has not
Tomorrow — whether assignments are scheduled, and how many tasks and workers
Status in the list
Each assignment row shows a confirmation status.
In progress — some workers have not confirmed yet (today)
All confirmed — everyone has confirmed
Partially unconfirmed — some workers never confirmed (past dates)
Scheduled — not sent yet (future dates)
No tasks assigned — announcement only, no task assigned
If someone has not confirmed
They have not checked in yet, or they checked in before the assignment was sent. Ask them to open the app.