Do List contains the list of tasks that are committed to be worked on for the Do Week by the main contractors and sub-contractors. It also contains the list of constraints falling in the Do Week to be updated as well as other constraints whose conditions fall in the Do Week. The Do List represents the committed weekly work plan of the project. If a work that is already committed in the Do List cannot be started in the week for due to some reason, it has to be uncommitted from the Do List and delayed to the appropriate date.
Do List displays:
Constraints tab - All the constraints falling under Do Week, conditions falling under Do Week and the conditions passed the Lookahead page with Not Done status.ย
Tasks tab - All the committed tasks to Do Week
List of Constraints under Do List
To learn more on how to update the progress of the Task read the article Update Task Progress.