The cleanup in Upcountry was completed in mid-January, as the quantity of ash and debris was a small fraction of the amount in Lahaina. The cleanup and transfer of ash/debris from Lahaina into the TDS site will extend into January 2025. Efforts are underway to expedite the planning, design and construction of a permanent disposal site (PDS) at the Central Maui Landfill, which could be completed in late 2024.