Below are 11 datapoints that is recognized by the OnTrack System. These columns can be in any order, but must contain the following information:

  • Position ID - Example: ABC-1 (MUST be Unique)

  • Date: Which will be the date of deployment. Available formats are:

    • MM/DD/YYYY | DD/MM/YYYY | MM/DD/YY | DD/MM/YY

  • Vendor: Vendor Name

  • Position: Level within the company (Line Guard, Supervisor, Manager, etc.)

  • Area of Responsibility: Area within the Event their position will be located in

  • Position Name: Exact position of the position/dot

  • # of Staff: If there are multiple staff at this individual dot or area, you can use numbers greater than 1

  • Priority: YES or NO (If you list out only priority dots, all empty cells will automatically be given NO priority)

  • Shift Start: (Can be 12 / 24 Hour)

  • Shift End: (Can be 12 / 24 Hour)

  • Rate: Total rate for the day (NOT hourly rate)

Example

TIP!
OnTrack will automatically validate these columns if they are named as shown. If there are any discrepancies in naming, you'll need to manually validate them in the next screen.