How to Configure Default Pre Solar Rate?

Why Does This Matter?

Setting the right utility rate is the foundation of every accurate proposal. With the ability to configure default pre-solar utility rates, your team can ensure every proposal starts with consistent, reliable data, without manual entry each time.

What You Will Need

  • Admin access to SubcontractorHub Platform.

Step-by-Step Instructions

Step 1: Click “Manage Database” and select “Database” from the dropdown.

Step 2: Click “Solar System” and select “Utility List” from the dropdown. You can also select from the other job types as well depending on your requirement.

Step 3: Click the “Default Pre Solar Rate” tab.

Step 4: Select the preferred utility provider, utility, and default pre-solar rate from the dropdown and click “Save”.