Integration requirements

In order to integrate Kojo and Procore, you must have:

  • A Kojo account

  • A Procore account that includes the Project Financials Commitments tool

To get set up with a Kojo account, please fill out the demo request form at https://www.usekojo.com/integrations/procore to get in touch with Kojo’s sales team.

Integration Map

The Kojo + Procore integration is a bidirectional sync. The data flow between the two systems is illustrated in the diagram below.

Syncing data from Procore to Kojo

Data syncs from Procore to Kojo automatically, every hour. You can see the last time data synced from Procore by navigating to the Integration Setup page within Kojo (Admin → Setup → Integration).

Syncing data from Kojo to Procore

  1. The PO must be in an “acknowledged” state before it can be synced to Procore.

    1. Send the PO to the vendor through Kojo.

    2. Within Kojo, mark the PO as acknowledged by the vendor.

  2. Open Kojo and navigate to the PO.

  3. Click the “Link to Procore” button.

  4. If any required fields are missing from the PO, you will see an error message - correct all errors, and click the “Link to Procore” button again.

  5. The PO will now be synced to Procore, and will show up in the Procore Commitments tool.