Add a Phase to the Project

Jetmir Abdija avatar
Written by Jetmir Abdija
Updated over a month ago

You can create new phases to structure the project flow according to its requirements. BlueDolphin offers you full flexibility to add or remove phases, as well as to rename any existing ones in a basic and empty flow.

You can add up to 10 phases in a project.

  1. Open the project and click the

    pencil icon.png

    icon in the top right corner to enable edit mode.

  2. Click the β€˜+’ (Add phase) button. One Untitled phase gets added to the project.
    ​

    add phase.jpeg
  3. Click the pencil icon to rename the phase title. Each phase title must be unique.
    ​

    rename the phase.jpeg
  4. Click Apply to save the changes.

Remove Phase

You can delete any existing or newly added phases from the project. Removing a phase will also delete all deliverables linked to it.

  1. Open the project and click the

    pencil icon.png

    icon in the top right corner to enable edit mode.

  2. Click the Pencil icon in the corner of the phase to to select Remove phase option.

Remove Phase.jpeg