Q: Can I change an existing contract from Lump Sum to GMP?
A: No, existing contracts cannot be converted to GMP. Only new contracts can be set up with the GMP contract type.
Q: How can I revert an amendment to draft?
A: To request an amendment to be reverted to draft, contact customer support using the chat icon in the bottom-right corner of the platform.
Q: Can I change the project settings contract type from Lump Sum to GMP?
A: This feature is not available at the moment. Stay tuned for future updates.
Q: What happens after the initial contract execution?
A: After executing the initial contract, you can begin creating amendments. Once all required amendments are finalized, you can proceed with executing the original contract.