Crop Plan Studio (the Plan page) keeps the reasoning behind a plan, not only the plan. Use it to record the issues a paddock is planned around and the decisions you made, see who changed what and undo a change, find out why one paddock differs from the rest, mark a pass as conditional, and test a different crop before you commit.
Where is the change history? It isn't in a paddock's tabs. In Crop Plan Studio, open Actions in the top bar (the ••• button on a phone) and choose Change history.
Before you start
Open Crop Plan Studio: on a computer select Plan in the top navigation. On a phone, go to More → Paddocks & crops → Crop Plan Studio.
Tap a paddock on the map to open its planning panel. To select several, turn on Select in the top bar (or Shift-click on a computer), tap each paddock, then press Done.
Recording notes, making passes conditional, Make same, Keep and Plan tools need permission to edit crop plans. Owners, co-owners and admins always have it; staff and advisers have it by default.
Record an issue the paddock is planned around
Select the paddock or paddocks and open the Notes tab. A number beside Notes says how many issues and decisions are recorded.
Select Record an issue….
Fill in Issue (ryegrass, radish, acidity, compaction, anything), Kind and How it is known: Observed, Measured, Suspected or From history. This keeps a suspicion from quietly becoming a finding.
Add Detail (optional), such as "resistant to Group 1, worst along the creek", and select Record.
Under Planned around, use Tie or untie an activity… to tie the issue to the passes that deal with it.
Phase then shows which passes address each issue, and flags "Nothing in this season's plan is tied to it" on paddocks where nothing does. If a pass that was tied to an issue is later taken out of the plan, the issue says so. Issues are never deleted: select Resolved when one is dealt with.
Record a decision and why
On the Notes tab, select Record a decision….
Fill in Decision ("Left the fungicide conditional"), Why ("pending a disease review at GS39"), Evidence (optional), and Look again if or Or on (a date).
Select Record.
Last season's decisions for the same paddocks show underneath, so the reasoning is there when the same question comes round again. Select No longer stands to retire a decision. Phase records what was decided; it never claims a decision caused how a season turned out. Decisions can be printed on the season plan PDF with Decisions and reasons.
Check the evidence for a decision
Select one paddock, open the pass's ••• menu and choose Evidence for this decision. It opens as a sheet. For a fertiliser, seeding or spray pass it shows what Phase holds that bears on it:
Fertiliser: the latest soil test with its date, depth and number of sample sites, this season's applied and planned nutrients, last season's fertiliser and your budget yield.
Seeding: the rotation, the last time the paddock grew this crop and what it yielded, and last season's weed, disease and pest notes.
Sprays: last season's chemistry with herbicide groups, and the crop's herbicide-tolerance trait.
Every line says where it came from, and a gap is shown as a gap. For the paddock's full records (rotation, past yields and soil tests), use Compare. Use these to review the plan, but confirm agronomic decisions with professional advice.
Make a pass conditional
Use this for work that is in the plan but not a commitment, like "second N top-dress, review at GS30".
Find the pass in the planning panel.
Select Add a detail, then Only if needed.
Tick Conditional: only if it is needed.
In Goes ahead if, say what would make it go ahead. Add a Review on date if you like.
Select Save changes.
The same tick-box is on the second step of Add a pass, and a saved template remembers that a pass is an option.
A conditional pass shows with a dashed edge, a Conditional tag (Only if needed while it is open) and its condition, and its cost reads "if done $28/ha". It stays out of the committed numbers everywhere:
paddock and farm input cost, break-even and margin
the season's planned nutrients
the Inputs list, where it shows beside the requirement as "+ 1.2 t possible"
the budget in Financial Performance, and Demand in Inventory
the adviser Products board and the season plan PDF's totals
Phase Agent's answers about how much product you need
Untick it to commit it again. Once it's done, it counts like any other completed pass. Phase never makes a pass conditional, or commits one, on its own.
See what changed: change history
In the Studio's top bar, open Actions → Change history. With paddocks selected, it shows only their history. Plan tools → Change history… on the paddock sheet opens the same thing, in the Studio and on a paddock's Plan tab.
Tap a row to see the before and after of every value, for example "Urea in Top-dress · rate: 100 kg/ha → 130 kg/ha", with the paddocks it applied to. Tap a paddock name to select it on the map.
Each row says what changed, who made it, when, and how: Edited by hand, From a template, Copied from another paddock, Carried forward from last season, Imported, Worked out by a calculator, or Asked of Phase with the words you used. One row is one change however many paddocks it touched, and an undo shows as its own row.
Edits on a paddock's Plan tab show too, labelled Edited on the paddock's Plan tab: adding, changing or removing a pass or product, applying edits to matching passes, and copying a plan or pass to other paddocks. Price fixes with Plan check's Use inventory price, and any change that brings a line up to today's inventory price, show as the line's cost per hectare, for example "cost: $0.80/ha → $0.76/ha".
History starts from 17 September 2026. Plan tab edits made before 15 October 2026 aren't in it.
Undo a change from the history
In Change history, tap one of your own changes to open it.
Select Undo this change. Phase shows what would go back, and on how many paddocks, before anything is written.
Select Undo change, or Keep it to leave it.
This works even after a reload, and the undo is recorded in the history. You can only undo your own changes, and only if your role can edit plans. When one can't be undone, Phase says why instead: the paddock has changed since, the work has been done since, a prescription or record is linked, the change was very large, it removed or swapped products, it set a figure whose unit the history doesn't keep, or it was in another season (open that season to undo it).
Find out why a paddock is different
Select paddocks of one crop. The planning panel says how many match the program most of them are on, for example "16 match · 4 differ". Open it to see each difference: "Urea at 130 kg/ha in Top-dress, the standard is 100 kg/ha", "No glyphosate in Pre-emergent", "an additional activity: Snail bait", a different seed or water rate, or a pass that is conditional on one paddock only. Each shows its cost per hectare, a count across paddocks, and, where the history knows, how it came about.
Make same brings that paddock onto the standard in one change you can undo.
Make all same does every paddock with that difference as one change.
Keep records your reason ("sandy country gets the extra"). Select Keep it to save it. The reason is shared with everyone on the farm and the difference isn't raised again unless the value changes. Stop keeping reverses it.
Make same changes only the pass or product the difference is about; a paddock holding the same pass twice keeps the one that matches. Phase never treats a difference as a mistake on its own.
Test another crop first
Select the paddocks, then open Plan tools (the ••• at the top of the paddock sheet).
Choose What changes if another crop went in….
Pick the crop under These paddocks went into and, if you've saved one, the program under On this program.
Phase runs the change on a copy, so the real plan isn't touched. Recalculated for you shows hectares by crop, committed input cost, each product's requirement before and after and any shortfall, whole-farm nutrients, planned work, budgeted production, and whether plant-back was checked. Yours to decide lists what Phase won't settle: no program for the new crop, paddocks still carrying the old crop's yield and price (left out of the new crop's production until you set them, because a wheat yield is never counted as a canola yield), the same crop two years running, and production falling below what is contracted.
Select Take this to the plan… to apply the same change through the usual preview, or Leave the plan as it is.
A paddock already in that crop is left alone and listed as an exception.
The old crop's planned (never completed) work can't stand under a new crop. With a program chosen, it is replaced by that program. With no program chosen, it is cleared and nothing is put in its place.
Completed work always stays. Phase doesn't choose a program, variety or rate to fill the gap.
Good to know
Make same isn't for tidying two spellings of one variety. Use Change beside the crop's name instead: see Build a crop plan from scratch.
You can also ask these questions in the Studio's Agent (on a phone, Actions → Agent), such as "Why is Creek Flat different?" or "What still needs a decision?": see Ask Agent in Crop Plan Studio to change the plan.
The Spatial shortcut on the season overview (with nothing selected) opens the zone-map workspace, and Vary by zone in Spatial… under a product's ••• starts a prescription for that line. Phase Spatial needs Phase Ultra: see Set rates and export a prescription.
If something doesn't look right
There's no Record or Plan tools button. Your role can see plans but not edit them.
Evidence for this decision has moved. Since 7 November 2026 it is in the pass's ••• menu, not under the pass's facts. It shows when one paddock is selected.
Undo this change isn't offered. It's only on your own changes that haven't been undone already, and only for people who can edit plans.
An older change isn't in the history. History starts on 17 September 2026 (15 October 2026 for Plan tab edits).