PPC Insights

Understand whether teams are completing pinned tasks on time using the PPC Insights Dashboard

Sarah Cusack avatar
Written by Sarah Cusack
Updated over 9 months ago

PPC Insights displays a collection of data specific to the PPC and Variance Reasons compiled across the project portfolio in Touchplan. It is critical that project teams Promise Work Weekly to ensure that commitments are tracked weekly and accurate PPC can be tracked.

PPC is 20% of the Performance Index and the metrics can be found on company, portfolio, and project analytics dashboards.

PPC (Percent Plan Complete) is a reliability metric that calculates what percentage of weekly commitments were met ‘On Time’ in Touchplan over a specific period of time. Touchplan displays promises (or commitments) as black “pins” located on the finish date of the respective tickets. When tickets are marked as complete-- the pins will change color to display red, blue, or green depending on whether the work has finished early, late, or on time in relation to the pinned commitment. For example: the number of green pins divided by the total number of pins (for a specified period of time) = PPC %

Overdue Promised Tasks is the number of task tickets that have been pinned in the past 6 weeks but have not been updated as completed and still have a black pin. Click on the Overdue Promised Tasks number in the tile to see a list of all the tickets or scroll down to the Overdue Promised Tasks tile at the bottom of the Dashboard.

The PPC table shows metrics including PPC, Total Promises and Overdue for projects in an account.

Top Variances is a metric that shows the most used variances reasons for pinned task tickets updated as completed early, late or not updated at all.

PPC by Week is a metric that shows the pinned task tickets completion rate. The green line shows the number of pinned task tickets that week and the blue bar represents the PPC for that week.

PPC by Role shows a select number of roles across the account and how many pinnned task tickets they marked as completed on time. The green line shows the number of pinned task tickets a specific role over the past 6 weeks and the blue bar represents the PPC for a specific role over the past 6 weeks. (how do the roles displayed get picked)

Variance by Week is a metric that shows the variance reasons for pinned task tickets marked as completed early, late or not updated for the past 6 weeks.

Variance by Role is a metric that shows the variance reasons for pinned task tickets marked as completed early, late or not updated by role over the last 6 weeks.

Variance Report is a detailed tile that shows the variance reasons, planned v actual start/finish dates and more for pinned task tickets that have not been update as completed on time.