To import tickets into Touchplan:
Customize the project date range by filtering in P6 prior to exporting
Note: Touchplan allows for a maximum of 4,000 rows of data to be imported at one time
Note: this only needs to be done one time for each project
Step 3: In Touchplan, move the Active Line in the desired plan out to the end date of the ticket import
Step 4: In Touchplan, import the P6 .xslx file following the steps below
Determine the data source and define the parameters of the import
Check for any errors or warnings within the file
Choose an insertion point for the new tickets in the plan
Update matching tickets
Note: you will only be prompted to go through Step 4 if there are multiple tickets with the same External Schedule ID.
Add Variance Reasons to Completed Tickets
Note: you will only be prompted to go through Step 5 if a ticket from Step 4 was pinned in Touchplan.
To learn how to export tickets from a Touchplan project in a P6 format click here.