Effective November 18, 2026. This SOP is Exhibit D to the WXLLSPACE Owners Mural Agreement. It explains what owners, property managers, general contractors and our project teams need to have in place before, during and after mural installation.

1. Purpose and Who This Applies To

This SOP covers site safety, access, wall readiness, installation planning, equipment, protection, documentation and coordination for WXLLSPACE mural projects.

It applies to WXLLSPACE personnel, artists, subcontractors and vendors, and to Owner representatives, property managers, general contractors and anyone else involved in site access or installation.

2. Installation Planning

Before mobilization, WXLLSPACE will confirm the following with Owner by email or through our project tools:

  • Proposed start and completion dates

  • Estimated on-site work days

  • Equipment and access needs, including lifts, scaffolds, staging and barricades

  • Who is responsible for surface preparation

  • Site rules and access requirements provided by Owner

  • Insurance certificates (COIs) and Additional Insured information required before mobilization

  • Onsite contacts for both sides

Owner should review these details and flag any conflicts before mobilization.

3. Pre-Installation Site Review

Before mobilization, WXLLSPACE may do a basic visual review of the approved wall and work area, looking at accessibility, visible surface condition, prior coatings, visible leaks or moisture, nearby finished surfaces or sensitive materials, equipment access, active construction conflicts, and pedestrian or vehicle circulation.

This review is visual, non-destructive and advisory only. It is not a structural, engineering, environmental, hazardous materials, moisture or concealed-condition inspection, and it is not a substrate warranty. WXLLSPACE does not perform abatement, remediation, structural repair, environmental testing or hazardous materials removal.

4. What Owner Should Disclose Before Mobilization

Owner should share all known or reasonably available information that could affect the Work, including:

  • Wall composition and prior coatings

  • Leaks, moisture issues or structural concerns

  • Hazardous materials or environmental conditions

  • Access, security, gate, key, badge, elevator or loading dock requirements

  • Active construction conditions

  • Tenant or resident restrictions and operational constraints

  • Parking, loading or utility access limits

  • Nearby sensitive surfaces, vehicles, landscaping, signage or equipment that need protection

  • No-photo, privacy or brand restrictions

Owner should also provide any available records about wall composition, prior coatings, environmental issues or structural conditions.

5. Wall Readiness

Approved walls should be clean, dry, sound, accessible and suitable for mural installation before WXLLSPACE mobilizes. Unless the Agreement, an Exhibit or a Change Order says otherwise, Owner is responsible for:

  • Wall repairs and patching

  • Cleaning

  • Moisture mitigation and correcting active leaks

  • Substrate corrections and primer application

  • Removing loose paint or unstable coatings

  • Correcting unsafe wall conditions

  • Providing safe, reasonable access to the mural area

If a wall is not ready, accessible, safe or suitable, WXLLSPACE may delay mobilization or installation. Resulting delay, remobilization, equipment, standby and coordination costs may be Owner-caused Impact Costs under the Agreement.

6. Site Access and Logistics

Owner, the property manager or the general contractor should provide:

  • Approved access dates and hours

  • Loading, unloading and parking access

  • Utility access reasonably needed for the Work

  • Secure storage and restroom access, if available

  • Elevator or loading dock access, if applicable

  • Gate codes, keys, badges or check-in procedures

  • Onsite, property management and general contractor contacts

  • Site orientation requirements

  • Any tenant, resident or public notification requirements

  • Any other site-specific access rules

7. Active Construction Sites

On an active construction site, Owner or its general contractor should provide all site requirements before mobilization, including safety rules, orientation, PPE, check-in/check-out, restricted areas, work hour limits, other trades near the mural area, equipment and staging restrictions, closure and barricade requirements, emergency procedures and the superintendent’s contact information.

New restrictions imposed after mobilization that materially affect schedule, cost, access, equipment or performance may require a Change Order or be treated as Owner-caused Impact Costs.

8. Lifts, Scaffolding and Fall Protection

  • Access equipment should suit the site, wall height, work area and installation method.

  • Lifts, scaffolds and mechanical equipment should be operated only by qualified, trained or licensed operators where the law requires it.

  • Equipment should be inspected as required by law, manufacturer guidance and site rules; defective equipment is taken out of service until fixed.

  • Areas below or next to elevated work should be controlled, marked or barricaded where appropriate, with spotters used when moving lifts or vehicles.

  • Fall protection (guardrails, lift baskets, harnesses, anchor points or other compliant systems) should be used where required by law, OSHA, site rules or manufacturer guidance.

  • Work at height may be paused for wind, storms, lightning, unstable surfaces, equipment instability, unsafe access or other safety concerns.

Owner should disclose conditions that affect equipment, such as slab load limits, pavers or finished flooring, overhead obstructions or power lines, ceiling heights, ramps, slopes, soft ground, drainage structures, and width, doorway or gate clearances. Equipment extensions caused by Owner delay, inaccessible sites, unready walls or new site restrictions may be Owner-caused Impact Costs.

9. Unsafe Conditions and Weather

WXLLSPACE may pause affected Work when conditions are unsafe or would compromise the installation, including storms, lightning, excessive wind, extreme heat, rain or wet surfaces, surface temperature or curing limits, active leaks, unstable substrate, hazardous materials, exposed electrical hazards, unsafe access, uncontrolled pedestrian or vehicle traffic, or unsafe lift or scaffold conditions.

Owner is responsible for correcting unsafe site conditions not caused by WXLLSPACE, the Artist or WXLLSPACE Personnel. Weather delays extend the schedule, and WXLLSPACE will resume work when conditions allow. Delays or costs from Owner-controlled conditions may be Owner-caused Impact Costs.

10. Protection, Overspray and Housekeeping

  • WXLLSPACE uses reasonable precautions, such as masking, drop cloths, plastic sheeting, temporary containment and floor or surface protection, to reduce overspray, staining and dust.

  • Special containment or protection beyond ordinary mural practice may require a Change Order.

  • WXLLSPACE keeps the immediate work area reasonably orderly and removes ordinary debris from its Work.

  • Damage caused by WXLLSPACE operations will be corrected within a commercially reasonable time after written notice.

  • WXLLSPACE is not responsible for damage caused by Owner, tenants, residents, third parties, weather, site defects, other trades or conditions outside its reasonable control.

11. Work Area Controls and Temporary Closures

WXLLSPACE will coordinate with Owner on staging areas, barricades, pedestrian and vehicle controls, lift movement, resident or tenant access, loading zones, temporary closures, restricted areas and any public-facing safety signage. Closures should be limited to the affected work area when practicable.

12. Incidents and Stop-Work Directives

WXLLSPACE will notify Owner after becoming aware of a material safety incident, citation, violation, stop-work order, reportable injury or material near miss involving the Work. The notice will include, as far as known, the date, time and location, the people involved, what happened, immediate corrective action and next steps. Emergencies are handled immediately under applicable law and site procedures. Owner or its general contractor should provide any required incident reporting procedures before mobilization.

Owner may direct an immediate stop to affected Work for an imminent safety hazard, as set out in Section 8 of the Agreement. The directive should identify the specific hazard.

13. Photography and Drones

WXLLSPACE documents its Work as described in Section 10 of the Agreement and makes reasonable efforts to avoid capturing confidential or restricted areas, or identifiable residents, tenants, guests or employees without permission. Owner should disclose any no-photo, privacy, security or brand restrictions before mobilization. Drone or specialized recording must comply with applicable law and will be coordinated with Owner in advance.

14. Completion Deliverables

At completion, WXLLSPACE may provide:

  • Date-stamped completion photographs and the Substantial Completion notice

  • Final walkthrough notes and documentation

  • The Mural Care & Maintenance Guide

  • Expense reports, closeout documentation or COIs, if required

15. Relationship to the Agreement

  • This SOP supplements the WXLLSPACE Owners Mural Agreement and is incorporated into it as Exhibit D.

  • If this SOP conflicts with the signed Agreement, the Agreement controls, unless the Agreement expressly adopts a stricter project-specific requirement.

  • Exhibit A, Exhibit B or a signed Change Order may modify or add to this SOP for a specific project.

  • The version of this SOP in effect on the Agreement’s Effective Date applies, unless the parties agree otherwise in writing.