Create a Material Requirements Plan (MRP)

Create a Material Requirements Plan (MRP) in BRAINR to turn MPS planning into actionable production.• Identify required raw materials and allocate production to lines. • Generate orders aligned with the Master Production Schedule (MPS). • Use the results to align planning and execution.

MRP converts the Master Production Schedule (MPS) into detailed requirements and orders.• Considers raw material availability, production capacity, and operational constraints. • Gives a complete view of what to produce, when, and with which materials.

Important Notes

If you add products manually here, they are not linked to a customer/address. • Label data will not be sent to labeling machines. • Fix it by opening the generated order later and filling the customer/address before printing/processing labels.


Open the MRP Application

  1. From the Homepage, go to the "Production Requirements Plan (MRP)" app located in the Production Planning section.

  2. The app displays all existing MPS records in one of the following statuses:

    • Draft

    • Open

    • Calculated

  3. Click + Create Schedule to start a new MRP.


Configure the MRP Header

Fill in the required header details:

  • Description – Enter a clear, descriptive name for your schedule.

  • Type – Choose between:

    • Forecast: For advance planning.

    • Operational: For current or active production planning.

  • Period – Select from predefined options like Today or Tomorrow, or define custom start and end dates.

    (Available options may depend on your organization’s configuration.)


Provide Input Data

Supply BRAINR with the key information for calculating production requirements. You can:

  • Import MPS File.

  • Import via CSV File.

  • Manually add the values:

    1. In Products section, click + Add Product to open modal.

    1. Fill required fields:

      • Product– Select from dropdown.

      • Qty to Produce – Enter production quantity.

      • Qty to Reserve – Optional stock reservation.

      • Qty to Order – Optional purchase quantity.

      • Unit – Select unit of measure.

    1. Click "Add and Close" to add the product and close the modal, "Add" to add and keep the modal open, or "Cancel" to close without saving.


Save Your Plan

Click Save or Save and Calculate (top-right or bottom-right corner).

  • Save: Saves MRP as Open status for later edits and calculations. Returns to MRP list.

  • Save and Calculate: Runs MRP calculation and opens the plan detail view showing a Gantt chart of production requirements by line and dates.