Create Ticket Import Data Source Using Oracle Primavera Cloud (OPC)

Note: Projects must create a data source to link their files to prior to using the ticket import feature

Written by Corrine Shuler

Important: Oracle Primavera Cloud (OPC) is currently available on a limited-release basis

Before you can create an OPC data source in your project, you must contact the Touchplan Support Team through Live Chat or by emailing support@touchplan.io. Our team will need to enable Primavera Cloud (OPC) as an available data source on your project before you can proceed with the setup steps below.

Once OPC has been enabled for your project, follow these steps to create your data source:

Create a Primavera Cloud (OPC) Data Source

  1. Click the three-dotted button next to the project name.

  2. Select Project Settings.

  3. Under the Data Sources drop down menu, click Create New Data Source.

  4. Enter a Data Source Name (for example, Primavera Cloud File).

  5. From the Data Source Type dropdown, select Primavera Cloud.

  6. Select a Ticket Time Resolution:

    • Day – Import ticket durations in days.

    • Time/Hours – Import ticket durations in hours and minutes for plans with Precision Time Planning enabled.

  7. Enter a WBS Separator

  8. Click 'Save'

For more information on how to import tickets into Touchplan from Primavera Cloud click here.