What is a Production Routing?
A Production Routing defines the step‑by‑step manufacturing process across work centers, including the activities (resource quantities) required at each step. In BRAINR, it typically includes:
Work Centers: Locations responsible for executing stages of the process.
Activities: Quantities assigned to each work center (costing is handled in the ERP; BRAINR focuses on operational management).
Quality Controls: Checks or tests that must be performed at specific moments in the route.
Where to create a Production Routing
Create a new Production Routing
Click + Create Route in the top‑right corner.
Under General Data, fill in the required fields:
Code
Name
Product
Reference Qty
Unit of Measure
Valid From
Add work centers
On the same page, add the Work Centers for the route.
For each work center, fill in:
Work Center
Code
Name
Order
If the route has only one work center, mark it as Default.
If the route has multiple work centers, mark as Default only the work center where activity confirmations and product inputs and outputs are performed.
Add activities
Expand each work center and click + Activity.
For each activity, fill in:
Activity
Quantity
Unit
Code
Name
Order
Save the Production Routing