Climate First Bank, powered by OneEthos, offers a 70/30 funding structure for solar projects. Under this structure, funding is divided into two milestones:

  • M1: 70% at installation completion and lender verification.

  • M2: Remaining 30% at passed inspection and approval of required documents.

M1: Initial Funding – 70%

The initial 70% funding milestone requires the solar installation to be completed and verified.

Required documentation:

  1. As-built engineering plan set

  2. AHJ-approved construction permit

  3. Completed lender inspection confirming the system has been installed

  4. Customer approval to release funds

Lender Inspection Requirements

Once installation is complete and ready for verification, the installer must request a lender inspection through the portal.

Depending on project conditions, the borrower may be required to provide photos, additional information, or property access to complete the inspection.

Inspection Fees

  • Initial inspection: No fee for the first visit.

  • Rescheduling fee: If the installer indicates the project is ready but the installation cannot be verified, additional review may be required and a $70 rescheduling fee will apply.

M2: Final Funding – Remaining 30%

The remaining 30% funding milestone requires a passed AHJ inspection and approval of the required documentation.

Required documentation:

  1. Proof of passed AHJ inspection

  2. Proof that Permission to Operate (PTO) has been requested from the utility

  3. Signed lien waiver release

  4. Customer approval to release funds

Note: Fully approved PTO is not always required for this funding milestone. Documentation confirming that PTO has been requested from the utility, such as an Interconnection Application, is sufficient. However, if neither a permit nor an inspection is required for the project, fully approved PTO must be provided.

Roofing Funding (If Applicable)

For eligible projects that include roofing, 100% of the approved roofing cost may be released before M1 and M2 funding upon completion of the roofing work and approval of the required documentation.

Required documentation:

  1. Required roofing permit

  2. Proof of passed roofing inspection

  3. Signed roofing lien waiver

  4. Customer approval to release funds


Important: All funding releases are subject to review and approval of the required milestone documentation. Missing, incomplete, or unacceptable documentation may require additional review.