Skip to main content

Change one paddock's plan on its Plan tab

Read a paddock's Plan tab, change a rate, remove a product, and update matching copies on other paddocks.

P
Written by Phase Team

A paddock's Plan tab shows its crop plan for the season. Use it to change a rate, a date or a product, add or take off a pass, mark a pass done, and pass an edit on to the same job on other paddocks. It is the same plan sheet as Crop Plan Studio, so a pass works the same way in both. To change many paddocks at once, use Crop Plan Studio.

The quick answers. Every pass reads open, with nothing to expand. To change a rate, tap it, type the new one and select Save. To change anything else on a pass, tap its small pencil (the date beside the pass type, the water rate, droplet, nozzle, method, target and the rest), change it and select Save just under it. Add and Edit under the products open the step-by-step card on the pass. To change the date a finished job was done, see Fix what was applied, or reopen a finished job.

Before you start

  • Open the tab from Map: tap the paddock, then tap Plan. It shows the season selected in Phase.

  • Changing the plan needs permission to edit crop plans. Without it you can read the plan, but nothing on a pass can be changed, and Add and Plan tools don't show.

  • Mark done needs a separate permission, Record completed work. See Mark work as done.

Change a product's rate

You can change the rate on any pass that isn't done yet.

  1. Tap the product's rate, which reads as words with a pencil, such as "2 L/ha ✎". On a computer, type the new rate in place and pick the unit. On a phone, the number pad opens.

  2. Check the cost under the rate.

  3. Select Save under the row. Cancel puts the old rate back.

The changed figures roll to their new values: the rate, its cost, the pass total and the season's $/ha. A message offers Undo. A rate or price that would make the line cost more than $1,000 a hectare asks first, under the row; it usually means a decimal point or a unit went wrong. If the same pass is planned on other paddocks, Phase then offers to change them too (see below).

Change a product's price, swap it or take it off

Tap the product's name. Its menu has Change the price…, Replace with another product…, Vary by zone in Spatial…, Move up and Move down, and on the map Smart swap product… (when an equivalent is in stock), Product details… and the label. Remove from this activity turns the line into Keep and Remove; nothing comes off until you tap Remove. When Inventory has a new price for a product, the question shows under it.

Add to a pass, or edit it

  • Add, under the products, opens the card on what goes on the pass: its products with − and + on their rates, a × to take one off, and the same product search, equipment and costs as a new pass.

  • Edit opens the card on the pass's details as they are (water, droplet, nozzle, method and the rest). The ticket says Save changes, and only what moved is saved. On a phone the step it opens on has X to close without saving.

  • Add a detail lists the details not set yet, such as droplet size, nozzle, pressure, speed, Part of the paddock, Only if needed and Note for the operator. Tap one to set it.

  • The pass's ••• menu has Edit this pass… too.

Part of the paddock. A spray, spread, apply, harvest or operation pass can be planned over part of the paddock: Add a detail → Part of the paddock → Part of it, then a % of the paddock or hectares. On a harvest (including Mow or cut, Bale and Chop for silage), everything on the pass follows that part: the machine and contractor costs, the bales or tonnes planned and the products. A spot spray keeps its machine costs on the whole paddock, because the sprayer still drives all of it. See Plan or record a spot spray or part of a paddock.

Pass an edit on to matching paddocks

After you save a change, if the same open job was planned on other paddocks before your edit, Phase opens Apply edits to matching activities?, with the matching paddocks ticked.

  1. Untick any paddock that should stay different.

  2. If product or equipment lines changed, leave Copy product and equipment changes ticked to copy them too, or clear it to copy only details such as timing, water rate or notes.

  3. Select Apply to N fields, or Not now to keep the change on this paddock only.

How matches are found. Phase compares the activity type, its name (ignoring extra spaces and capitals), the water rate, and every product with its rate and unit, as they were before your edit. A conditional pass never matches a committed one. Only open passes in the selected season are offered; finished work is never changed. Dates aren't part of the match, so untick any paddock that should keep its own timing. Only what you changed is copied.

Add or remove a pass

  • Add a pass: select Add, pinned to the foot of the sheet. It opens one card that asks one question at a time: the kind of pass (or Cost on its own), when, the details, what goes on it, then Add to the plan. See Build a crop plan from scratch. A paddock with no plan shows, for example, No plan for 2026, and opens Start season setup first, for a Target yield (t/ha) and Target price ($/t), then Continue to activity.

  • Remove a pass: open its ••• menu and select Remove from 1 paddock, then confirm. It can't be undone on the map; in Crop Plan Studio, Undo brings it back.

A finished pass has no Remove. To correct a finished job, use Edit what was applied, or reopen it: see Fix what was applied, or reopen a finished job.

Mark the next pass done

The next pass to do carries a Next label and Mark done. Mark done opens a card on the pass, one question at a time, each already filled from the plan, so Next is often all it takes. Its arrow holds Done on another date…, Done on part of the paddock… (on every kind of pass) and Record what was actually applied…. Once recorded, the pass settles with Reopen, and a message offers Undo for six seconds. Any other pass is marked done from its ••• menu. See Mark work as done.

What the Plan tab shows

The top: the season (for example "2026 season") and its planned $/ha, with Plan tools beside it: New recommendation, Copy this plan to other paddocks…, Shift dates…, Save plan as a template, Save a pass as a template… (and Save a pass to my library… for advisers) and Change history…. Then the crop line (crop and variety, any pasture sown under it, hectares, $/ha and total) with Details, and the nutrients as four rings, N, P, K and S, applied against planned.

The crop is whatever the plan is saved as. A paddock planned as Fallow or Pasture shows that crop with no seeding pass; with passes planned it reads, for example, Fallow · passes planned. A plan with no crop and no seeding pass reads Crop not set. On a farm with two crops in one crop year, a Summer | Winter switch opens the other half.

The passes run in planned-date order, each one open. Once something is done, Sort by switches between Planned date and Date completed. A pass shows:

  • Its name, kind, date (with a pencil), $/ha and hectares, who has it if it was given out, and a Reco badge if it came from a recommendation. A pass marked done with no signal says "Done, waiting to sync".

  • On a spray, the pale-blue water band: the water rate, the droplet size and the nozzle as its ISO colour and size, and Fill for Fill Assist. Under it, one row with the note for the operator and the pass's nutrients in kg/ha.

  • Each product with its rate, the cost under the rate and how much the paddock needs ("Need 390 L"), then the pass total, and the method, target and other details as small labels with pencils.

  • Add and Edit under the products, and Mark done on the next pass.

  • The first spray still to do shows one row of conditions: the verdict in words, Delta T, the wind, the station and the time, with Best hour for a dial of the next 24 hours (Earlier, Later and Next good hour). A done pass shows the conditions it was done in.

  • The pass's •••: Edit this pass…, Mark done…, Assign to someone…, Add note (on the map), Evidence for this decision, Edit what was applied (on a done pass), Copy this pass to paddocks…, Vary by zone in Spatial…, Save as template and Remove from 1 paddock.

A finished pass has an Actual | Plan switch, and Edit what was applied in its ••• menu.

Good to know

  • Adding and marking done, one step at a time. The first time someone who knew the old forms opens a plan sheet, a note says so: everything works as it did, Add and Mark done are step by step, and a pencil changes a detail on a pass.

  • A finished pass keeps the rates it was recorded with: correct those with Edit what was applied.

  • The cost counts every plan the paddock has for the season, as the Studio and Finances do, and leaves conditional passes out (they show as Possible under Details).

  • Plan tab edits show in Change history as Edited on the paddock's Plan tab.

  • Not on the Plan tab. What-if another crop, Not cropped this season…, clearing the plan and Import a PDF… are in Crop Plan Studio.

If something doesn't look right

  • I can't find Open all passes, or a pass won't open. Every pass reads open now; there is nothing to expand.

  • I can't find Add activity or New Reco at the top. Add and New reco are at the foot of the sheet. New recommendation is also the first item in Plan tools.

  • The ••• beside a product is gone. Tap the product's name for its menu.

  • The matching question didn't appear. No other paddock's pass matched, or nothing you changed could be copied. Your edit is still saved here.

  • The rate won't save. Check for a missing decimal point. A rate must be above 0, and a price question under the row needs an answer first.

  • I can't tap the rates or see Add. You need permission to edit crop plans, and the pass must not be done.

Related