The quote for a Pluginvest charging station includes at least:

  • the technical audit (remote)

  • the basic installation package

  • the charging station

  • the mandatory inspection by an independent inspection body

In 80% of home installations, the required installation work is covered by the basic installation package.

In addition, the quote may also include additional work, selected options, and/or desired monthly services.

What’s included in the basic installation package:

  • Wall-mounted installation

  • 15 meters of cabling (power and data)

  • Modifications to the fuse box, including the addition of a circuit breaker and residual-current device

  • 1 wall drilling

  • 2 meters of excavation works in soil

If the technical audit shows that all necessary work falls within the basic installation package, no additional installation costs will be charged. This audit can, in most cases, be carried out remotely.

What is considered additional work?


Additional work may include things like additional cabling or breaking open a driveway. These are charged based on fixed unit rates per linear meter. Your prior approval will always be requested.