Export Tickets from Touchplan to P6 Using the P6 XER Format

Save time with the Ticket Export feature to export tickets into P6

Written by Corrine Shuler

Export tickets from Touchplan back into Primavera P6 using the P6 XER format to transfer schedule information between the two platforms.

Recommendation: For the cleanest export into P6, we recommend ensuring that your master schedule tickets in Touchplan are connected with logic ties. You can:

  • Manually add logic ties to tickets in Touchplan by following the steps here.

  • Import activities with logic ties already included by following the import steps here.

Step 1: Create a P6 XER Template

Before exporting tickets, create a P6 XER template to use when exporting data from Touchplan to P6.

Step 2: Export Tickets from Touchplan

Once your P6 XER template is ready:

  1. Click the three-dot menu at the top of the Phase Plan List.

  2. Select Export Tickets.

  3. From the Export Format drop-down menu, select P6 Primavera XER.

  4. Click Choose Template and upload the most recent XER schedule from your computer.

  5. Set the desired filters, including: Start and end date, phase plans, location, roles, and external linkage.

  6. Click Run Report.

  7. Once the report is complete, click Download.

Important: The P6 XER export is designed to transfer and update schedule information between Touchplan and P6 rather than function as a true two-way synchronization. Any Touchplan tickets that share an External Schedule ID with a ticket in P6 will replace the corresponding P6 ticket when the exported schedule is imported into P6.

For additional information about the Ticket Export feature, see the Ticket Export Solution Note.