Company Analytics gives corporate managers and executives the insights they need to understand the status of the enterprise project landscape. That data will help them form and implement strategies and best practices to ensure optimum performance for existing projects and enable the rapid and standard setup of new projects.
Drill into more dashboards by clicking the Additional Dashboards button along the top of the Dashboard.
Total # Projects v Inactive # Projects will display which projects in the portfolio are considered 'Inactive' in Touchplan. A project is deemed 'Inactive' if any actions listed below have NOT occurred in the project in the last 21 calendar days:
A user has viewed a plan in the project
A user has added a ticket in the project
A user has edited a ticket in the project
A user has moved a ticket in the project
The Performance Index will measure a team’s use of tasks, milestones, and constraints. These metrics will indicate how well the team is maintaining its plans. The Performance Index includes metrics on the company's PPC, Milestone PPC, Constraint Performance and Status Performance.
PPC (Percent Plan Complete) is a reliability metric that calculates what percentage of weekly commitments (pinned task tickets) were met ‘On Time’ in Touchplan over the past 6 weeks.
Status Performance measures the number of tickets that have been statused (marked as completed early, on time, or late) versus the total number of tickets created in the past 6 weeks.
To access the PPC Insights, Status Performance, Milestone PPC, Constraint Insights, Team Participation, Labor Insights, Swim Lane Insights, and Task Quick View Dashboards select Additional Dashboards.